CAG Flags Major Lapses in Implementation of Rural Power Scheme in J&K, Ladakh | KNO

“62% works left incomplete”, Ministry cites unexpected events, tendering issues, hostile terrain

Published

on

kno news

Srinagar, Dec 24 (KNO): A performance audit by the Comptroller and Auditor General (CAG) has exposed major lapses in the implementation of the Deen Dayal Upadhyaya Gram Jyoti Yojana (DDUGJY) in Jammu & Kashmir, including Ladakh. The audit report tabled in the Parliament on December 18, a copy of which lies with news agency—Kashmir News Observer (KNO), reveals that Jammu & Kashmir and Ladakh failed to complete 62.62% of its sanctioned work before the scheme’s closure in March 2022. Audit also observed that 20 States/UTs could not execute the quantum of work ranging between 3.31 per cent and 62.62 per cent till the closure of the scheme. Particularly, Jammu and Kashmir, Ladakh, and Tripura could not complete 62.62 per cent and 20.72 per cent of their respective sanctioned project costs. In its response to audit observations, the Union Ministry of Power stated that delay in J&K was due to unexpected events. “In respect of Jammu & Kashmir, it was stated that delays happened due to unexpected events i.e., issues in tendering, hostile terrain,” the report said. The Centre had launched the scheme-‘Deen Dayal Upadhyaya Gram Jyoti Yojana’ (DDUGJY) in December 2014 to provide continuous and reliable electricity supply to rural areas through feeder separation, strengthening of distribution infrastructure, and rural electrification initiatives DDUGJY guidelines stipulated that in a project, the work was to be completed within 24 months from the date of issue of Letter of Award in case of turnkey contract and within 30 months in case of partial turnkey contract/departmental execution. The Monitoring Committee overseeing the implementation of DDUJGY, in its 23rd meeting held on December 21, 2021, instructed state distribution companies (DISCOMs) to take up only those works that could be completed by December 31, 2021. It was also conveyed that works executed beyond December 31, 2021 shall not be funded under the scheme—(KNO)

Trending

TOP STORIES2 hours ago

PM Modi led regime brought lasting peace to J&K: Amit Shah | KNO

TOP STORIES2 hours ago

Year-Ender 2025: Srinagar Airport handles 35.26 lakh passengers, 21,576 flights despite challenges | KNO

TOP STORIES2 hours ago

Cold conditions prevail in J&K, snow chances loom over next week | KNO

TOP STORIES2 hours ago

Srinagar Smart City website remains offline for over three months | KNO

TOP STORIES2 hours ago

‘Worm infestations, poor iron intake major causes of rising Anaemia in children’ | KNO

TOP STORIES3 hours ago

J&K Education 2025: confronting hard truths, tackling crises | KNO

TOP STORIES3 hours ago

CAG Flags Major Lapses in Implementation of Rural Power Scheme in J&K, Ladakh | KNO

TOP STORIES3 hours ago

North Kashmir: In 2025, Police register 202 FIRs, nab 272 accused, seize 240 vehicles | KNO

TOP STORIES3 hours ago

Traffic moves slowly on Jammu-Srinagar Highway, other roads remain closed | KNO

TOP STORIES3 hours ago

Traffic Police intensify enforcement drives to ease congestion on city roads | KNO

TOP STORIES3 hours ago

Kargil getting key health push with Centre’s support: LG Ladakh | KNO

TOP STORIES3 hours ago

IGP Kashmir chairs Security Review Meeting at PCR Kashmir | KNO

TOP STORIES3 hours ago

Srinagar police attach property of notorious drug peddler under NDPS Act | KNO

TOP STORIES3 hours ago

LG's Greetings on the eve of Christmas | KNO

TOP STORIES3 hours ago

CM Omar extends Christmas greetings | KNO

TOP STORIES3 hours ago

Div Com Kashmir for In-Situ De-Addiction Mechanism in Educational Institutions | KNO

TOP STORIES3 hours ago

Director Information condoles demise of Subash Mehra, Editor in Chief of Jammu Jottings | KNO

Copyright © 2021